Afghanistan : Transport Network Development Investment Program - Tranche 3

road

Distance

178 km
new
178km
rehabilitated
– km
existing
– km

Cost

$230m
$230,000,000

operational

2021

Objective

"Better connectivity and efficiency through a fully complete North-South Corridor."-ADB

Description

Physical interventions under Tranche 3 include 178 km of reconstructed national road from Dar-i-Suf to Yakawlang linking the roads already completed under the ADB financed North South Corridor Project.

History

The project was scheduled to complete in 2017. The schedule was revised to be 2021. It is unclear whether the project is operational.

Finance

logo
$220m grant
Asian Development Bank
Bank
logo
$10m investment
Government of Afghanistan
Government

Governing authorities

Sources